A1.7 Critical control points
Last updated
Last updated
Australian Drinking Water Guidelines 6 2011, v3.9
Go back to NHMRC websiteAppropriate selection of critical control points is an important consideration, as increased focus in process control (monitoring and documentation) for a water supply system will be directed toward these activities and processes. The identity and number of critical control points is system specific and will be determined by the range and magnitude of potential hazards and associated risks. Identification of critical control points may be aided by the use of a decision tree, as shown in Figure A1.2.
Critical control points have several operational requirements, including establishing an appropriate monitoring regime specifying specific parameters and critical limits to ensure the process or activity operates effectively. Failure to meet a critical limit represents loss of control of the process and an unacceptable health risk, either directly, through the supply of unsafe water, or indirectly, where multiple critical control points exist, by exceeding the capacity of subsequent processes. Corrective actions must also be available to re-establish process control when criteria have not been met.
If there is a deviation from a critical limit corrective actions also must be available to reduce the health risk from hazards present in the system.
Assess preventive measures from catchment to consumer to identify critical control points.
Identify procedures required for processes and activities from catchment to consumer, including microbial health-based targets (see Section 3.4 Operational procedures and process control).
Document the critical control points and criteria.
Table A1.9 provides examples of potential sources of Giardia, preventive measures and potential critical control points from catchment to consumer for a river system. In combination, these need to achieve the LRVs described in Table 5.5. Table A1.10 provides further detail on potential critical control points and operational criteria.
แต Preventive measures should be applied from catchment to consumer in accordance with the multiple barrier approach. Overall, when considered together, these preventive measures should prevent or reduce the hazard to an acceptable level.
แต Drinking water systems generally include numerous preventive measures and strategies that all contribute to assuring the safety of water supplied to consumers; however, only a limited number are amenable to selection as critical control points. The identification of critical control points is system specific and involves making judgments based on knowledge of the potential hazards and associated risks, and the preventive measures. Each significant hazard identified should have a critical control point. However, there may be more than one critical control point to address the same hazard, and more than one hazard may be prevented or reduced by a specific critical control point. Appropriate selection of critical control points is an important consideration because the focus in process control (monitoring and documentation) will increasingly be directed toward these processes and activities. Too many critical control points may make the system unwieldy and too few may fail to provide adequate assurance of drinking water quality.
แถ Important considerations are that the preventive measure is essential for significantly reducing the given hazard and that the effectiveness of the measure has been validated.
แต Operational control must be provided for the preventive measure to assure its ongoing effectiveness. This includes establishing a monitoring regime to ensure the process or activity operates to requirements. Practicalities of monitoring should be considered. Operational parameters and criteria must be monitored with sufficient frequency to guarantee the critical control point is providing protection against targeted hazards and to reveal any failures in a timely fashion. Corrective actions must be available to regain control immediately when criteria have been exceeded or deviated from.
แต Failure means deviation from a critical limit not from a target criterion (see Section 3.3.2 and 3.4.2). The significance of critical control points is that failure of the process or activity represents an out-of-control hazard. A practical consideration is whether failure of the process or activity (ie loss of control) will result in a (potentially) unacceptable health risk and require immediate notification of the health regulator.
Groundwater abstraction
Enteric bacteria, viruses and protozoa from septic and livestock waste; nitrates
Physical surety of bore and radius of protection zone. Absence of E. coli. NOโ 50 mg/L (as nitrate)
Weekly inspection and testing for presence of E. coli. 6-monthly monitoring of nitrate
Repair fault in bore
Enforce protection zone
Catchment water reception at take off weir prior to reservoir
Higher levels of enteric bacteria, viruses and protozoa from septic and livestock waste following heavy rainfall
Set flow rate and turbidity limits at location upstream of weir
Continuous stream monitoring station
Divert flow away from reservoir intake
Reservoir mixing/ destratification
Cyanotoxins
6500 cells/mL
Target value: 1000 cells/mL
Continuous monitoring of temperature and dissolved oxygen through the water column
Regular sampling; increase frequency following detection of cyanobacteria or in summer
Dose reservoir with copper sulfate
Improve efficiency of mixing
Take reservoir out of service
Filtration
Enteric bacteria, viruses and protozoa
Combined filtered water turbidity < 0.5 NTU 95% of time. Maximum 5 NTU
Target value: < 0.3 NTU at all times
Continuous online monitoring
Identify problem and take action (e.g. repair faulty operation)
Increase coagulant dose
Filter backwash
Primary disinfection and storage
Enteric bacteria, viruses and Giardia
Free chlorine residual > 1 mg/L
Detention >x (to set minimum C.t)แต
Continuous online monitoring and alarms with automatic feedback to chlorine dosing
Flow not to exceed x ML per hr
Increase chlorine dose
Decrease flows to increase detention time
Stop supply
Secondary disinfection
Enteric and free-living bacteria
Free chlorine residual >1 mg/L
Continuous online monitoring and alarms with automatic feedback to chlorine dosing
Increase chlorine dose
Stop supply
Distribution of treated water
Enteric bacteria, viruses and protozoa
Chemical contaminants
Minimum free chlorine residual of 0.2 mg/L at specified locations
Positive pressure at specified locations
Continuous online monitoring
Hydraulic pressure
Increase chlorine dose
Identify and repair source of pressure loss
C.t = contact time; E. coli = Escherichia coli; NTU = nephelometric turbidity unit แต see Section A8 Chlorination as an example of a critical control point